Inspection Information

Required Inspections

Stage of Construction Type of Inspection
After excavation, before pouring concrete Footer Inspection
Crawl Space - after block is laid. Foundation Inspection
Basement after forms are placed, before pouring concrete Basement Walls
Prior to pouring basement floor or slab Underfloor Plumbing
Before enclosing walls with wall boards, etc. Framing
Before enclosing walls with wall boards, etc. Rough-in Electrical
Before enclosing walls with wall boards, etc. Rough-in Plumbing
Before enclosing walls with wall boards, etc. Rough-in Heating A/C
Prior to utility hook-up Electrical Service Entrance
Prior to occupancy of structure Final Inspection

If you have any questions about this information please call (574) 372-9548.

Building Commissioner Testing Smoke Alarm